Choose the correct option.
A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of the work. In how many days will the work be completed ?
A15 days
B22 days
C25 days
D35 days
Answer: Option (Login/Signup)
Show Explanation