111. A man's basic pay for a 40 hour week is Rs. 20. Overtime is paid for at 25% above the basic rate. In a crertain week, he worked overtime and his total wage Rs. 25. He, therefore, worked for a total of :
Answer:
Explanation:Here is no explanation for this answer
Workspace
MindTree HCL Technologies Wipro NLTH
112. If A alone can do a piece of work in 8 days and B alone can do the same work in 12 days. How many days A and B required to finish the same work if they work togather?
Answer: 24/5 days
Explanation:A alone one day work = 1/8
B alone one day work = 1/12
Both A and B one day work = (1/8 + 1/12) = (3/24 + 2/24)
= 5/24
so A and B together finish the work in 24/5 day
or 4 4/5 days.