41. A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone ?
Answer: 60 days
Explanation:A's 1 day's work = x
and B's 1 day's work = y
So (A & B) 1 day work = 1/30 => x+y =1/30
=> 30x + 30y = 1 -------- (1)
So 16x + 44y = 1 -------- (2)
By Solving above two equations,
x = 1/60 and y = 1/60
B's 1 day's work = 1/60
Hence, B alone shall finish the whole work in 60 days.
Workspace
Global Edge TCS NQT
42. Which of the following option be replaced in ___(A)___?
Answer:
Explanation:Here is no explanation for this answer
Workspace
TCS NQT
43. Which of the following option be replaced in ___(B)___?
Answer:
Explanation:Here is no explanation for this answer
Workspace
TCS NQT
44. Which of the following option be replaced in ___(C)___?
Answer:
Explanation:Here is no explanation for this answer
Workspace
TCS NQT
45. Which of the following option be replaced in ___(D)___?
Answer:
Explanation:Here is no explanation for this answer
Workspace
TCS NQT
46. Which of the following option be replaced in ___(E)___?
Answer:
Explanation:Here is no explanation for this answer
Workspace
TCS NQT
47. Which of the following option be replaced in ___(F)___?
Answer:
Explanation:Here is no explanation for this answer
Workspace
TCS NQT
48. Which of the following option be replaced in ___(G)___?
Answer:
Explanation:Here is no explanation for this answer
Workspace
TCS NQT
49. Which of the following option be replaced in ___(H)___?
Answer:
Explanation:Here is no explanation for this answer
Workspace
TCS NQT
50. Which of the following option be replaced in ___(I)___?
Answer:
Explanation:Here is no explanation for this answer
Workspace
TCS NQT