Quantitative Aptitude :: Time and Work - Discussion

Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion

84 / 100

Choose the correct option.

A works thrice as much as B. If A takes 60 days less than B to do a work then find the number of days it would take to complete the work if both work together?

A221 days

B221/2 days

C223/2 days

DNone of these

Answer: Option (Login/Signup)

Show Explanation

Asked In :: CGI