A and B can do a piece of work in 12 days, B and C can do it in 15 days and C and A can do the same work in 20 days. How long would each take to complete the job?
A1/30, 1/20, 1/60
B1/20, 1/30, 1/30
C1/20, 1/20, 1/20
D1/60, 1/0, 1/30