Sixteen men can complete a work in twelve days. Twenty four children can complete the same work in 18 days. 12 men and 8 children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?

A2 days

B4 days

C6 days

D8 days

Answer: Option (Login/Signup)