Choose the correct option.
A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days 4/7 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A21
B91
C81
D55
Answer: Option (Login/Signup)
Show Explanation
Asked In ::
STEP-BY-STEP
- M1D1H1/w1=m2d2h2/w2
- 117*33*8/(4/7)=x*13*9*7/(3/7)
- X=198
- Since there is 117 men total men's are complet remaining work 198 men
- 198-117
- 81
*