Quantitative Aptitude :: Chain Rule - Discussion

Home > Quantitative Aptitude > Chain Rule > MCQs Questions Discussion

8 / 57

Choose the correct option.

2 men and 7 boys can do a piece of work in 14 days; 3 men and 8 boys can do the same in 11 days. Then, 8 men and 6 boys can do three times the amount of this work in

A18 days

B21 days

C24 days

D30 days

Answer: Option (Login/Signup)

Show Explanation