Choose the correct option.

A can do a work in 10 days and B can do the same work in 15 days. So how many days they will take to finish the same work ?


A5 days

B7 days

C9 days

D6 days

Answer: Option D

Explanation:

First find the 1 day work of both (A & B)
A 1 day's work = 1/10
and
B 1 day's work = 1/15

So (A + B) 1 day's work = (1/10+1/15)
= (3/30+2/30) = 5/30 = 1/6

So Both (A & B) together can finish work in 6 days

Submit Your Solution


Here is the list of questions asked in Deloitte model papers for freshers Deloitte online test questions. Practice Deloitte Written Test Papers with Solutions and take Q4Interview Deloitte Online Test Questions to crack Deloitte written round test. Overall the level of the Deloitte Online Assessment Test is moderate. Only those candidates who clear the written exam will qualify for the next round, so practic all the questions here and take all the free tests before going for final selection process of Deloitte