Quantitative Aptitude :: Time and Work - Discussion

Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion

99 / 100

Choose the correct option.

If A alone does the work in 15 days,how much time will A and B take working together to complete the job,given that A is 30% more efficient than B?

A234/69

B585/69

C69

D585

ENone of these

Answer: Option (Login/Signup)

Show Explanation

Asked In :: Capgemini