Choose the correct option.
A does 4/5 of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work ?
A23 days
B37 days
C37 1/2 days
D40 days
Answer: Option (Login/Signup)
Show Explanation