Quantitative Aptitude :: Time and Work - Discussion

Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion

56 / 100

Choose the correct option.

A can do a work in 6 days , B can do a work in 8 days and C can do it in 12 days. B left work after 6 days. For how many number of days should A and C should work together to complete the remaining work ?

A1 Day

B2 Days

C1 1/3 Days

DNone of these

Answer: Option (Login/Signup)

Show Explanation

Asked In :: IBM

Post Your Answer Here:     

No Discussion on this question yet!