Quantitative Aptitude :: Time and Work - Discussion

Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion

11 / 100

Choose the correct option.

A can finish a piece work in 18 days and B can do the same work in half the time taken by A. So if they working together, what part of the same work can finished in a day?

A1/7

B1/6

C6

D5/6

Answer: Option (Login/Signup)