Quantitative Aptitude :: Time and Work - Discussion

Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion

40 / 100

Choose the correct option.

2 computers each produced 48000 public utility bills in a day. One computer printed bills at the rate of 9600 an hour and the other at the rate of 7800 an hour. When the first computer finished its run, how many bills did the other computer still have to print?

A2000

B1000

C9000

D8500

Answer: Option (Login/Signup)

Show Explanation

Asked In :: Capgemini