TCS Placement Questions & Answers :: TCS
641 / 652
In a particular year the month of January had exactly 4 Thursdays and 4 Sundays, on which day of the week, Jan 1 occurs?
AMonday
BTuesday
CThursday
DWednesday
Answer: Option A
Explanation:As there are 4 full weeks i.e 28 days.
So, every day occurs min 4 times.
Then remaining 3 days (as jan has 31 days) will be Monday Tuesday Wednesday. so on 31st Jan comes Wednesday.
So, 1st Jan will be MONDAY
Submit Your Solution
642 / 652
Average salary of 17 teachers is 45000.3 teachers left and the average salary dropped by 2500.What is the sum of salaries of 3 teachers who left?
A173000
B176000
C170000
D85000
Answer: Option C
Explanation:Total Initial Salary : 17*45000 = 765000
Average Salary After removal of 3 Teachers = 45000-2500 = 42500
Total Final Salary : 14*42500 = 595000
Sum of Salaries of 3 teachers who left : 765000 - 595000 = 170000
Submit Your Solution
643 / 652
Find a two digit number which is doubled and after that add +2 in it. and then reverse the number we would get the actual number.
(Example : xy * 2 = pq => pq+2 = xy )
A25
B34
C52
D26
ENone of these
Answer: Option A
Explanation:Lets assume the two digit number be 10x+y
Adding 2 after doubling the number is reverse of the number.
So 2(10x+y)+2 = 10y+x
19x -8y +2=0 ----- (i)
The above equation (i) satisfies for the value, x=2, y=5
So, the number = 10*2+5= 25
Submit Your Solution
644 / 652
Let a, b, c, d and e be distinct integers in ascending order such that(76-a)(76-b)(76-c)(76-d)(76-e) = 1127. What is a + b + c + d
A247
B274
C300
D287
Answer: Option B
Explanation:Product of 5 terms equal to 1127. As all the five terms are integers, given product should be a product of 5 numbers. Now factorize 1127.
1127 = 72 * 23 = 7 * 7 * 23
But given that all the a, b, c, d, e are distinct. And we are getting only 3 terms with 7 repeats.
Now the logic is, integers means positive and negative, 7 and - 7 possible and 1, - 1 also possible . As a,b, c, d, e are in ascending order, the factors should be in decreasing order. So (23, 7, 1, -1, -7)
Now a = 53; b = 69; c = 75; d = 77
a + b + c + d = 274.
Submit Your Solution
645 / 652
What is the average of the first 200 terms of the series
1, -2, 3, -4, 5, -6, 7......
A-1
B-1/3
C-1/2
D1/2
Answer: Option C
Explanation:1+3+5+7+9+11+13.........+199 i.e 100 terms and
sum of n odd natural numbers is n^2 i.e 100^2 =10,000
-(2+4+6+8+10+12...........+200) i.e 100 terms and
sum of n even natural numbers is n(n+1) i.e -(100(100+1))= -10,100
average of first 200 terms = (10,000+(-10,100))/200
=-100/200
=-1/2 Ans.
Submit Your Solution
646 / 652
If 43 times of two digit numbers is 34 times of two digit reverse no . and sum of number is 14 then what is the number?
A86
B68
C95
D59
ENone of these
Answer: Option B
Explanation:43 time the no. And 34 time the reverse no.
43(10x+ y)=34(10y+ x)
430x+ 43y= 340y+34x
430x+43y-340y-34x=0
To solve this equation become
4x-3y=0 -------------- (1)
Sum of no. And reverse no. Is 14
X+ Y= 14 ------------- (2)
To solve both equation value of x and y
X= 6 and y= 8
So, number will be 68
Submit Your Solution
647 / 652
Structure can be used
ATo hold different datatypes
BHave pointers to structure
CTo assign to one another
DAll the above
Answer: Option D
Explanation:Here is no explanation for this answer
Submit Your Solution
648 / 652
A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is:
A6 3/5
B8 1/2
C10 1/5
D13 1/2
Answer: Option C
Explanation:A's 1 day work = \(\frac{1}{14}\)
B' 1 day work = \(\frac{1}{21}\)
A left 3 day before the completion of work.
B's 3 days' work = \(\frac{1}{21} \times 3 = \frac{1}{7}\)
Remaining work = \(1 \times \frac{1}{7} = \frac{6}{7}\)
(A + B)'s 1 day's work = \(\left(\frac{1}{14} + \frac{1}{21}\right) = \frac{5}{42}\)
Now, \(\frac{5}{42}\) work is done by A and B = 1 day.
or
whole work done by A&B = \(\frac{42}{5}\)
\(\frac{6}{7}\) part of work done by A and B = \(\frac{42}{5} \times \frac{6}{7} = \frac{36}{5}\) days.
Hence, total time taken = (3+36/5)days = \(10\frac{1}{5}\) days.
Submit Your Solution
649 / 652
A can do a work in 10 days and B can do the same work in 15 days. So how many days they will take to finish the same work ?
A5 days
B7 days
C9 days
D6 days
Answer: Option D
Explanation:First find the 1 day work of both (A & B)
A 1 day's work = 1/10
and
B 1 day's work = 1/15
So (A + B) 1 day's work = (1/10+1/15)
= (3/30+2/30) = 5/30 = 1/6
So Both (A & B) together can finish work in 6 days
Submit Your Solution
650 / 652
Tea worth Rs. 126 per kg and Rs. 135 per kg are mixed with a third variety in the ratio 1 : 1 : 2. If the mixture is worth Rs. 153 per kg, the price of the third variety per kg will be:
ARs. 175.50
BRs. 180
CRs. 170
DRs. 169.50
Answer: Option A
Explanation:Here is no explanation for this answer
Submit Your Solution
Here is the list of questions asked in TCS Aptitude Test Question with Answers page 65. Practice TCS Written Test Papers with Solutions and take Q4Interview TCS Online Test Questions to crack TCS written round test. Overall the level of the TCS Online Assessment Test is moderate. Only those candidates who clear the written exam will qualify for the next round, so practic all the questions here and take all the free tests before going for final selection process of TCS