Quantitative Aptitude :: Time and Work - Discussion
Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion
107 / 100
Choose the correct option.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
A23 days
B37 days
C40 days
D\(37 \frac{1}{2}\) days
Answer: Option (Login/Signup)
Show Explanation
Asked In ::
No Discussion on this question yet!