Quantitative Aptitude :: Time and Work - Discussion

Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion

364 / 100

Choose the correct option.

A alone can do 1/4th of the work in 2 days. B alone can do 2/3th of the work in 4 days. If all the three work together, they can complete it in 3 days so what part of the work will be completed by C in 2 days?

A1/12

B1/8

C1/16

D1/20

Answer: Option (Login/Signup)

Show Explanation

Asked In :: TCS SSC CGL Tier I