Quantitative Aptitude :: Time and Work - Discussion
Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion
364 / 100
Choose the correct option.
A alone can do 1/4th of the work in 2 days. B alone can do 2/3th of the work in 4 days. If all the three work together, they can complete it in 3 days so what part of the work will be completed by C in 2 days?
A1/12
B1/8
C1/16
D1/20
Answer: Option (Login/Signup)
Show Explanation
Asked In ::
No Discussion on this question yet!