X takes 4 days to complete one-third of a job,Y takes 3 days to complete one-sixth of the same work and Z takes 5 days to complete half the job.If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.
A6 days
B7 days
C5.1 days
D8.1 days
Answer: Option (Login/Signup)