Choose the correct option.
If 20 men or 24 women or 40 boys can do a job in 12 days working for 8 hours a day, how many men working with 6 women and 2 boys take to do a job four times as big working for 5 hours a day for 12 days?
A8 men
B12 men
C26 men
D24 men
Answer: Option (Login/Signup)
Show Explanation
Asked In ::
STEP-BY-STEP
Amount of work done by 20 men = 24 women = 40 boys
i.e 5man = 6 woman = 10 boys. -----------------(i)
According to the 1st condition, 5 men can do a job in 12 days working for 8 hours a day.
Required :- how many more men are required to work with 6 women and 2 boys.
Let the required number of men be M.
According to the given information,
=>(5 x 12 x 8 )/1=[(M 5 1) x 5 x 12 ]/4. ( 6 women= 5men