Sixteen men complete a work in 24 days while 48 children can do it in 16 days. Twelve men started the work, after 14 days 12 children joined them. In how Many days will all of them together complete the remaining work?
A15 days
B14 days
C10 days
D12 days
Answer: Option (Login/Signup)
Show Explanation
Asked In ::
STEP-BY-STEP
16M*24=48C816
so,M/C=48*16/16*24
S0,M:C=2:1
total work=16*2*14=768 unit.
let remaining work will be finished in xX days.
ATQ,12*2*14 (12*2 12)X=768
X=12