Choose the correct option.
A is 6 times as fast as B and takes 100 days less to complete a work than B. find the total no of days taken by A and B to complete the work.
A17/7 days
B120/7 days
C121/7 days
DNone of these
Answer: Option (Login/Signup)
Show Explanation