Choose the correct option.
A does 4/5 of work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
A37 days.
B37 1/2 days.
C35 days.
DNone of these
Answer: Option (Login/Signup)
Show Explanation
Asked In ::
SHORTCUT
A can do 4/5th works in 20 days.
so he can do the whole work in 20*(5/4) =25 days.
remaining work after done 4/5 by A is=1-(4/5)=1/5
(A+B) can do the 1/5th work in 3 days.
means the can do the whole work in (3*5)=15 days.
so,(A+B)'s 1 days work=1/15
B's 1 day's work {(1/15)-(1/25)}=2/75
so B can alone do the whole work in 75/2,means in 37 1/2 days.
Read Full Answer
Report Error
Please Login First Click Here
STEP-BY-STEP
In two days A, B and C together can finish 1/2 of a work and in another 2 days B and C together can finish 3/10 part of the work. Then A alone can complete the whole work in.
Read Full Answer
Report Error
Please Login First Click Here