Quantitative Aptitude :: Time and Work - Discussion

Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion

68 / 100

Choose the correct option.

A does 4/5 of work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

A37 days.

B37 1/2 days.

C35 days.

DNone of these

Answer: Option (Login/Signup)

Show Explanation

Asked In :: Wipro