A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in :

A1/9

B9 3/5

C9 2/5

D9 4/5

ENone of these

Answer: Option (Login/Signup)