[Updated] Goldman Sachs Aptitude Test Questions and Answers
Practice List of TCS Digital Coding Questions !!!
Take 50+ FREE!! Online Data Interpretation Mock test to crack any Exams.

Quantitative Aptitude :: Time and Work - Discussion

Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion

15 / 100

Choose the correct option.

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is:

A6 3/5

B8 1/2

C10 1/5

D13 1/2

Answer: Option (Login/Signup)

Show Explanation

Asked In :: TCS Accenture Cognizant MindTree

Post Your Answer Here:     

Reply    
Rate This: +0 -0
    Report


Report Error

Please Login First Click Here

Reply    
Rate This: +1 -0 +
    Report


Report Error

Please Login First Click Here

Reply     |    Rate This: +0 -0      |     Report     



Report Error