12 / 100

Choose the correct option.

A and B can do a piece of work in 45 days and 40 days respectively. They began to do the work together but A leaves after some days and then B completed the remaining work in 23 days. The number of days after which A left the work was :

A6

B8

C9

D12

Answer: Option (Login/Signup)

Show Explanation