Choose the correct option.
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone ?
A30 days
B40 days
C60 days
D70 days
Answer: Option (Login/Signup)
Show Explanation