Note 1

Take Note:

Take a note while surfing.





Note With Ink

Give your Note a Colorful Tag.




Easy to Access

Stay on same information and in Sync wherever you are.

Note 2

Take Note:

Organize your information,It may take Shape.





Think With Ink

Differ your Content by Color.




Easy to Access

Easy to pull up your content from anywhere anytime.

Note 3

Take Note:

Don't Let information to miss,Because it take shape





Note With Ink

Simple an Easy Way to take a note.




Easy to Access

Get the same in next visit.

Arithmetic Aptitude :: Time and Work

8. A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?

Answer: Option D

Explanation :

(A + B)'s 1 day's work = 1/30

so (A&B) 20 days work = (20*1/30) = 2/3

so left work = (1?2/3)=1/3

1/3 work is done by A = 20 days.

So whole work will be done by A = (20 x 3) = 60 days.

Asked In ::  Global Edge  