Choose the correct option.
X can do 1/4 of a work in 10 days, Y can do 40% of the work in 40 days and Z can do 1/3 of the work in 13 days. Who will complete the work first ?
Ay
Bz
Cx
DX and Z both
Answer: Option (Login/Signup)
Show Explanation
Asked In ::
TRICK
X-(10×4)=40
Y-(40×100/40)=100
Z-(13×3)=39
Z is very 1st complete the work