Quantitative Aptitude :: Time and Work - Discussion
Home > Quantitative Aptitude > Time and Work > MCQs Questions Discussion
41 / 100
Choose the correct option.
Amit want to make a 1000 m long wall with in 50 days he made a decision to hire 56 man however after 27 days amit realized that team was only able to make 448 meter wall find out the additional number of man that amit should employ as a mean of finishing work on the stipulated time.
A35
B49
C25
D52
Answer: Option (Login/Signup)
Show Explanation
Asked In ::
No Discussion on this question yet!