Choose the correct option.
Here 10 programers, type 10 lines with in 10 minutes then 60 lines can type within 60 minutes. How many programmers are needed?
A16
B6
C10
D60
Answer: Option (Login/Signup)
Show Explanation
Asked In ::
STEP-BY-STEP
10 lines - 10 minutes - 10 programmers are needed
10 lines - 1minute - 10*10=100 programmers needed. (Direct variation)
1 line - 1 minute - 100/10=10 programmers needed. ( Indirect variation)
1 line -60 minutes - 10/60 programmers needed. ( Indirect variation)
60 lines-60 minutes - (10*60)/60=10 programmers needed. (Direct variation)
10 lines - 1minute - 10*10=100 programmers needed. (Direct variation)
1 line - 1 minute - 100/10=10 programmers needed. ( Indirect variation)
1 line -60 minutes - 10/60 programmers needed. ( Indirect variation)
60 lines-60 minutes - (10*60)/60=10 programmers needed. (Direct variation)